Studi Evaluasi Kinerja Pembangkit Listrik Tenaga Hybrid Sebagai Penerangan Jalan Umum Di Lembaga Pelatihan Kerja Selaras Paiton

Putra, Angga Wijaya (2023) Studi Evaluasi Kinerja Pembangkit Listrik Tenaga Hybrid Sebagai Penerangan Jalan Umum Di Lembaga Pelatihan Kerja Selaras Paiton. Undergraduate thesis, Politeknik Negeri Jember.

[img] Text (Abstract)
ABSTRACT.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.

Download (34kB)
[img] Text (Bab 1 Pendahuluan)
BAB 1. PENDAHULUAN.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.

Download (45kB)
[img] Text (Daftar Pustaka)
DAFTAR PUSTAKA.pdf - Submitted Version
Available under License Creative Commons Attribution Share Alike.

Download (162kB)
[img] Text (Laporan Lengkap)
H41190522_LAPORAN LENGKAP.pdf
Restricted to Registered users only

Download (3MB) | Request a copy

Abstract

PT POMI's Lembaga Pelatihan Kerja Selaras Paiton in its history built a Renewable Energy Power Plant in 2019, the first to be built was a PLTMH with a capacity of 15 kW. The second is followed by building a PLTB with a capacity of 18 V 500 Watt. Then the third is building a PLTS with a capacity of 800 Wp 17.5 Vdc with 16 solar modules. Of the three Power Plants, they have a hybrid system and the generated power is channeled to Public Street Lighting as many as 8 lamps with a capacity of 35 Watt. As time went on from the installation of the Hybrid Power Plant there were various problems from the Generator and the Control Room. From these various problems it is necessary to carry out a performance evaluation. The method used to carry out the first evaluation for PLTS is to calculate the Performance Ratio. For PLTMH and PLTB calculate the output power generated by the Generator and Kiprok. The results showed that the highest PLTS PR was on the third day with a value of 40.2% and the lowest PR value was on the first day with a value of 31% which was caused by dust, temperature, angle of inclination and shadows, then for the PLTMH it produces a generator voltage starting from 22 V to 33 V adjusts to the water debit. Then for the PLTB it only produces a voltage of 0,1904 V and a current of 000.4 A due to inadequate wind speed. Furthermore, the battery energy value when charging is 2,411.95 Wh and when discharging is 1,777.6 Wh.

Item Type: Thesis (Undergraduate)
Contributors:
ContributionContributorsNIDN/NIDK
Thesis advisorFahriannur, AhmadNIDN25088907
Uncontrolled Keywords: Lembaga Pelatihan Kerja Selaras Paiton, PLTS, PLTMH, PLTB
Subjects: 410 - Rumpun Ilmu Teknik > 450 - Teknik Elektro dan Informatika > 451 - Teknik Elektro
Divisions: Jurusan Teknik > Prodi D4 Teknik Energi Terbarukan > Tugas Akhir
Depositing User: Angga Wijaya Putra
Date Deposited: 03 Jul 2023 07:01
Last Modified: 03 Jul 2023 07:02
URI: https://sipora.polije.ac.id/id/eprint/24426

Actions (login required)

View Item View Item